Naše referencie
Commissioning works references
Country and Project name: Date:
Works for SES TLMAČE Slovak boiler Company :
Czech Republic, Steelworks Třinec 1993/1994
Fluidized bed boiler with capacity 160 t/h of steam
Czech Republic, Power Plant Tisova, 1995/1996
Fluidized bed boiler with capacity 350 t/h of steam
Slovak
Republic, BEBA Bánovce nad Bebravou, 1997
Boiler house, 2x4t/h, 1,2MPa, 230°C
Slovak Republic, Petrochema Dubová, 1998
Boiler house, 2x4t/h, 1,2MPa, 230°C
Slovak Republic, PPC Bratislava, 1998
Cogeneration Power Plant
HRSG Boiler , 235 t/h, 8 MPa, 520°C
Czech Republic, Power Plant Praha
Malešice, 1998/1999
Coal Steam boilers 2 x 180 t/h, 9,6 MPa, 540°C
Slovak Republic, AD Štúrovo, 1999
Coal Steam Boiler , 125 t/h, 9,6 MPa, 540°C
Czech Republic, Power Plant Vresová, 1999/2000
Coal Steam boiler 325 t/h, 13,5 MPa, 540°C
Slovak Republic, EVO - Vojany, 2000
Fluidized bed boilers with capacity 2 x 325 t/h, 14,6 MPa, 540°C
Slovak Republic, Bučina Zvolen, 2001
Boilers for wood chips with capacity 2 x 16 t/h, 2,8 MPa, 380°C
Job position : Commissioning engineer, Service and start-up engineer ,
Works for ISTROENERGO GROUP Slovak Company :
Czech Republic, Power Plant České Budejovice, 2002
Coal Steam boiler 325 t/h, 13,5 MPa, 540°C
Turkey,AK
ENERJI - IZMIR
BATICIM , 2002/2003
Cogeneration Power Plant 43 MWe total power output
6 x GT Typhon 5,2 MWe
2 x HRSG dual pressure (3 x GT to one HRSG) + 1 x ST 16 MWe
Turkey, AK ENERJI – USAK 2003
Upgrading of USAK plant efficiency
Slovak Republic, Plastika Nitra, 2003
Steam Boiler , LOOS 1x8t/h, 1,2MPa, 220°C
Slovak Republic, SH – ENERGO Senica, 2003/2004
Boiler house, HKB 2x25t/h, 1,2MPa, 240°C
Poland, PEC Wysków
Waste Heat Hot Water Boiler 1 x 4,3 MWt 2003/2004
for Cogeneration Plant PEC Wyszków
Czech Republic, Steelworks Třinec, 2004
Reconstruction of
cooling system in Teplárna E2 -
I.Phase - Cooling tower Nr.1,2,3 New control system,
Turkey, NUH
ENERJI – ISTAMBUL 2005/2006
Cogeneration Plant 59 MWe of total power output
2 x GT GE 48,8 MWe + 2 x HRSG dual pressure + 1 x ST 26 MWe
Germany, IPO OBERBRUCH 2005/2006
New Cogeneration Plant based on GE LM6000 gas turbine-generator (GTG), with associated one Delivery and assembly of Heat Recovery Steam Boiler 46 t/h of steam
The Netherlands , DOW CHEMICAL COMPANY 2006
New Cogeneration Plant based on GE LM6000 gas turbine-generator (GTG), Heat Recovery Steam Boiler 46 t/h of steam ,
Slovak
Republic, Nuclear station, EBO J. Bohunice 2006
Stanby heating Plant HKB boilers 3 x 36 t/hr. Of steam with accesssories
"on key" form On base of contract BIDSF 0031009-A5B2/IEG-PMU
Bulgaria , Pleven 2007
Cogeneration Unit with GTG LM 2500 32,5 Mwe + HRSG 73t/hr.
With supplementary firing, 440°C; 39 barg,Control system, and electro part
Lithuania – Panevezio 2007/2008
New Cogeneration Plant based on GE LM6000 gas turbine-generator (GTG) with associated one heat recovery steam generator HRSG , Parameters: 40 t/hr; 6,52MPa; 482 °C
England, United Kingdom
- Wilton
Teesside 2008/2009
New Cogeneration Plant based on GE LM6000 gas turbine-generator (GTG) with associated one heat recovery steam generator (HRSG) 188t/hr.With supplementary firing, 385°C; 98 barg,
Czech Republic, Steelworks Třinec 2009/2010
New boiler for metalurgy 4 gases of power 80 t/hr., 495°C, 12 MPa,
Russia,
Mordovcement 2010
New Cogeneration Plant based on one (2) GE LM2500+ gas turbine-generator (GTG) with associated one (1) heat recovery steam generator (HRSG).
Slovakia,
Považská Bystrica 2011
New Cogeneration Plant based on one GE LM6000 gas turbine-generator (GTG) with associated one heat recovery steam generator (HRSG) and STG Siemens.
Parameters: 44 t/hr; 6MPa; 440 °C
Russia,
Syzraň 2012
New 220MW Cogeneration Plant based on 2 x 75MW GE Heavy duty gas turbine-generator (GTG) with 2 x associated one heat recovery steam generator (HRSG) and 1x 70MW STG Siemens.
Parameters: HP : 120 t/hr; 8MPa; 540 °C, LP : 20t/h, 0,55 MPa, 220°C
Slovak Republic, Power Plant
TEKO Košice, 2012/2013
New Coal Steam boiler 120 t/h, 13,5 MPa, 540°C
Extension of SCPP at Obajana, DANGOTE Nigeria , 2013
1 x Gas turbine generator (GTG) GE LM6000PC Sprint
Extension of SCPP at IBESE, DANGOTE Nigeria, 2014
2 x Gas turbine generator (GTG) GE LM6000PC Sprint
Heat Recovery Steam Generator Pakistan , 2014
Steam parameters: HP steam: 57 bar(a) / 408°C / 91 tph; LP steam: 7 bar(a) / 242°C / 31 tph
GTG type: 2 x GE LM6000 PC sprint, Steam turbine GE 35MW - France
Installation: Korangi CCPP, Karachi - Pakistan
HRSG supply by: Istroenergo Group, a.s. (IEG)
Works for FICHTNER – ENERGY
Company /MCC- Energy :
Czech Republic, Chemical Company LOVOCHEMIE , 2015
Supply by : ČKD Praha/MCC - Energy
Fluidized bed boiler with capacity 120 t/h of steam , 100 bar a, 535°C, Steam turbine Siemens 27MW,
Installation : LOVOCHEMIE a.s. Lovosice
Czech Republic , Power Plant CHotíkov
2016
Supply by : ČKD Praha /MCC - Energy
Boiler for waste combuscion : 40 t/h, 50 barg, 420°C, Steam turbine Siemens 10,5 MW,
Installation: Prvá Teplárenská Plzeň a.s.
Work for Slovenské Elektrárne a.s.
Slovak Republic, Nuclear power plant, EMO Mochovce 2017-2026
Power plant unit 3 and unit 4, reactor VVER 440/V-213 , 2 x 470MW,
Main Supply by : ENEL , Slovenské Elektrárne,
Commissioning for conventional island